SDLC blueprint

V-Model ceremonies → ceremony foundation

**Purpose:** Map **V-Model** design reviews and test gates to methodology-neutral **intent types** in [`ceremony-foundation.md`](ceremony-foundation.md).

V-Model ceremonies → ceremony foundation

Purpose: Map V-Model design reviews and test gates to methodology-neutral intent types in Ceremony foundation (methodology-neutral).

Canonical V-Model narrative: https://forgesdlc.com/methodologies-v-model.html · Wikipedia — V-model

Note: The V-Model's ceremonies center on left-side reviews (design gates) and right-side reviews (test gates). Below maps typical practices.


Practices / meetings × intent types

Common practice Foundation intents (primary → secondary) Notes
Requirements review C1 AlignC2 Commit Baseline requirements; agree acceptance approach. Top of the V.
Design review (system + detailed) C2 CommitC4 Inspect Approve design; confirm testability and traceability.
Test plan review C2 CommitC6 Assure Approve test strategy, traceability matrix, environment plan per V-level.
Development sync C3 Sync Coordination during implementation phase (bottom of V).
Test readiness review (TRR) C6 AssureC4 Inspect Gate: is the build and environment ready for testing at this V-level?
Test result review C4 Inspect Evaluate test outcomes; decide pass/fail/conditional at each V-level.
Acceptance review C4 InspectC1 Align Formal acceptance at top-right of V; deployment authorization.

C5 (Improve) in the V-Model is typically a post-project activity (lessons learned, process audit). Better teams add mid-cycle retrospectives during long development phases.


Tracking

Requirements traceability matrix (RTM) is the primary tracking artifact. It links requirements → design elements → test cases → test results across all V-levels. Maintain in docs/requirements/traceability/ or your ALM tool.


Suggestions (V-Model-specific)

Practice Suggestions
Requirements review Verify testability of each requirement. Vague requirements produce vague tests.
Design review Check traceability: does each design element map to a requirement? Does the corresponding test plan exist?
Test plan review Flag untested requirements explicitly. 100% coverage is the target; waivers must be documented.
TRR Do not proceed if the test environment does not match production configuration (where applicable).
Test result review Classify failures by V-level: a unit test failure is different from a system test failure in root cause and fix.
Acceptance Base acceptance on evidence (traceability, test results, compliance), not on opinions or partial demos.

Crosswalk to other methodologies: Methodology bridge — foundation intents ↔ named ceremonies.